Week 5 - Final Exam Points 50 Questions 50 Time Limit 720 Minutes Instructions Final Exam [WLO: 3] [CLOs: 1, 2, 3, 4, 5] Complete the exam, which will take approximately two hours but you have 12 hours available. This exam will be open-book. The exam consists of multiple-choice and true or false questions and is worth 20% of your course grade.Click on the Take the Quiz button when you are ready to start this exam. When finished, click on Submit Quiz.
Question 1
- / 1 pts
A project’s completion time variance is calculated by?Correct!
Summing the variances of the critical path activities
Multiplying the variances of all of the project activities
Summing the variances of all of the project activities
Multiplying the variances of the critical path activities
Question 2
- / 1 pts
Forecasting demand and translating that forecast into desired levels of purchasing, production, and distribution activities is part of which of the eight key supply chain processes?Correct!
Demand management
Customer service management
Customer relationship management
Manufacturing flow management
Question 3
- / 1 pts
A firm releases a new product that is unexpectedly very popular. It is likely that the firm will have to rely on which type of inventory function?
Transportation
Cycle
Hedge
Correct!
Safety stocks
Question 4
- / 1 pts
The set of task descriptions for a project is known as a(n)?
Bill of materials
You Answered
Task listing
Activity diagram
Work breakdown structure
Question 5
- / 1 pts
Activities on the critical path have slack times of?You Answered
Cannot be determined from the information given
>1
1
Question 6
- / 1 pts
The ISO standard associated with quality management is?Correct!
ISO 9000
ISO 12000
ISO 14000
ISO 10000
Question 7
- / 1 pts
All of the following are terms for material flow mapping except?
Value stream mapping
Process flowcharting
Correct!
Process value mapping
Process mapping
Question 8
- / 1 pts
The purchasing cycle is often broken down into a process with how many steps?
4
Correct!
6